The overload operation of concrete mixer

2013-08-26 17:00:33


Concrete mixer is to cement, sand and gravel aggregates and water are mixed and mixed into the concrete mix machinery. Concrete mixer mainly by the mixing drum, feeding and discharging mechanism, water systems, the prime mover, transmission, chassis and supporting devices and other components.

Concrete mixer machine overload operation is as follows:

A. Determined by the ratio of water volume of concrete needed, and adjust the time continued water supply to the corresponding point is time.
B. Start mixing concrete mixer motor running.
C. Close the discharge doors in the hopper add the required mixture, the lifting. Hopper should run smoothly and can freely stop anywhere on the track. If slippage should be first placed in the hopper bottom of the pit, and then adjust the brake motor big nut. Hopper upgrade properly, reliable braking after mixing tube feeding simultaneously to start the pump to the mixing tube water.
D. In concrete mixer machine mixing 25-35S, start the discharge gate discharge.
E. In the above commissioning process, if found to be not normal circumstances, you should immediately stop inspection, troubleshooting, and then in the second trial until normal. Concrete mixer machine new machine after running for a day at the lining and other bolts, nuts Check all fastening. Parts of transmission lubrication grease lubrication.